CDOT makes substantial progress ahead of US 50 Blue Mesa Middle Bridge limited opening (2024)

Montrose, Gunnison and Hinsdale Counties — The Colorado Department of Transportation is pleased to announce the limited opening of the US 50 Blue Mesa Middle Bridge ahead of the Fourth of July holiday weekend. With the first phase of repairs complete, emergency vehicles and those in smaller vehicles can start crossing over the US 50 Middle Bridge at 6:30 a.m. Wednesday, July 3. County Road 26 will remain open and maintained as a detour, and Kebler Pass is now open as well, as a seasonal route.

“CDOT anticipates delivering on our goal of opening the Blue Mesa Middle Bridge to limited traffic ahead of July 4,” said CDOT Executive Director Shoshana Lew. “We continue to work towards completing needed repairs ahead of winter. Over the course of the holiday weekend, the bridge will be open for 12 hours a day, which we hope encourages tourism in this area as these communities are still very much open for business. Starting on July 8, we will settle into a twice-a-day opening schedule to allow crews to continue to work on repairs throughout the day.”

For the long holiday weekend, one lane will be open on the bridge, and pilot cars, at slow speeds, will lead single-direction traffic between the hours of 6:30 a.m. to 6:30 p.m. through Sunday, July 7. After the long holiday weekend, beginning Monday, July 8, the bridge will be open, and pilot cars will lead single-direction traffic each day from 6:30 a.m. to 8:30 a.m. and again from 4:30 p.m. to 6:30 p.m.

Eastbound US 50 Montrose to Gunnison

Eastbound US 50 traffic (going towards Gunnison) will be stopped at the County Road 26 turnoff that is the current detour location. This stopping point is 0.5 mile west of the Middle Bridge. At this stop, traffic will be separated by which vehicles are allowed over the Middle Bridge and which vehicles have to take the County Road 26 detour, see below for more details on allowable vehicles.

Westbound US 50 Gunnison to Montrose

Vehicles traveling westbound on US 50 (going towards Montrose) will see signage during the passage times at the CO 149 and US 50 intersection, which will allow traffic that meets the restriction criteria (see below for more details on allowable vehicles) to proceed on US 50 to the crossing point along with traffic that are wishing to camp/fish/recreate along the north shore of the reservoir. All other vehicles that do not meet the restriction criteria will need to continue on CO 149 to the County Road 26 detour. Signage will be updated at US 50 and CO 149 at the end of the access window (6:30 p.m.) directing all westbound traffic to use CO 149 to the County Road 26 detour.

Approved for crossing over the US 50 Middle Bridge:

  • Passenger Vehicles
  • Pickup Trucks
  • Vans
  • Motorcycles
  • Emergency vehicles, ambulances and fire trucks

Required to utilize County Road 26 detour:

  • RV/Campers
  • Motorhomes
  • Trucks pulling trailers (boats, campers, side by sides)
  • Semi-trucks
  • Buses

CDOT leadership will host an in-person and virtual public meeting on Tuesday, July 2, from 6:30 p.m. to 8 p.m. in the Gunnison County Courthouse, 200 E. Virginia Ave., on the second floor to outline the limited opening schedule and discuss next steps for the continued bridge repairs. To join the meeting online, go to bit.ly/BlueMesaBridge.

Members of CDOT’s team will be out on Wednesday morning to provide refreshments and cookies to the motorists lined up at the closure points starting at 6:30 a.m. as a show of appreciation.

Crews have completed the first stage of critical repairs on the bottom flange, the horizontal part of a l-shaped beam, of the US 50 Middle Bridge. Working from a temporary scaffolding suspended from the side of the bridge, crews began the process of bolting four plates in four locations on Wednesday, June 12. This first phase of the repair process addressed areas that posed an imminent risk to structural integrity. Each plate location’s assembly is about 23 feet long, 2 ½ feet wide and 2 ½ inches thick, weighing approximately 9,000 pounds. More than 200 bolts were needed to secure each plate in place.

Currently, crews are modifying the expansion joints on the bridge to prepare for traffic on July 3. This weekend, crews will be preparing for quick deck access so that repairs can begin on the top flange on July 8, with bottom flange global repairs starting in August 2024.

Lake Fork Bridge Lane Closures

As CDOT works toward the limited opening of the US 50 Blue Mesa Middle Bridge, crews are now looking at potential repair work for the Lake Fork Bridge, located on the west side of Sapinero, and anticipate lane closures this weekend. Crews will be installing strain gauge sensors, which will monitor the effect of traffic loading on the structure and will be used to analyze effects of construction activities, such as initial milling operations as crews move into the inspection and repair phases of the Lake Fork Bridge. CDOT is currently planning single lane closures on the Lake Fork Bridge on Friday, June 28 through Monday, July 1 from 7 a.m. to 5 p.m. to install the sensors.

Detour Routes:

County Road 26 continues to serve as a bypass around the bridge closure for travel between Gunnison and Montrose. This detour route is open for seven releases in each direction every day except Wednesdays when there are five releases in each direction. Each Wednesday there is a midday closure to allow crews to safely make repairs to the road, when staff and materials are available. The State of Colorado legal maximum vehicle dimensions and weights will be enforced. This allows trailers and heavier commercial vehicles to use the bypass.

Vehicles traveling through Colorado should utilize the alternate state highway detours to the north and south (Interstate 70 and US Highway 160) instead of County Road 26 if possible. To maintain the local access route as a viable, safe bypass, traffic is managed using pilot vehicles. It is a high mountain native surface and gravel road.

Along with County Road 26, Kebler Pass is now open for the season to help ease travel through the area. Kebler Pass restrictions include no vehicles over 30,000 pounds, no vehicles longer than 50 feet and no hazardous materials.

Starting June 26, Gunnison CR 26 will allow overweight and over-width traffic. These loads, in excess of 85,000 pounds and/or over 8 1⁄2 feet in width and/or 14 1⁄2 feet in height and/or truck tractor semitrailer combinations that exceed 70 feet, require special permitting on both state and County roads. Oversize-Overweight vehicles are required to comply with state regulations found at: https://leg.colorado.gov/content/size-and-weight-limitations

Extra-Legal permits (permit) must be obtained prior to entry into Colorado or prior to movement of the vehicle/load. In order to travel CR 26 both state and County permits must be obtained. At a minimum, obtaining the approved permit by noon the day before the movement of the vehicle/load should be followed to ensure that the trip can proceed. These vehicles will proceed during the regularly scheduled release times.

Travel will only be permitted during the following release times on only Wednesdays for Oversize-Overweight loads.

Eastbound release times are 6:30 and 8:30 a.m. and westbound release times are 7:30 and 9:30 a.m. Each traffic release window is 30 minutes.

For state permits contact the Colorado Department of Transportation at 1-800-350-3765 or through https://coopr.codot.gov/

For County permits contact Gunnison County Public Works at 970-641-0044 or email [emailprotected] or online at https://gunnisoncounty.org/157/Public-Works.

A hotline and email address continue to be available to assist customers with questions about the local access route and US 50 bridge closure. Anyone with questions can reach out via 970-648-4423 or [emailprotected]. Calls are closely monitored and receive a prompt reply. Information is also available on the project website at bit.ly/us50bridge. Travelers should refer to COtrip.org or the smartphone COtrip Planner app to plan an alternate route.

Travel Impacts

  • US 50 is closed between Montrose and Gunnison
  • Recommended alternate routes are I-70 to the north or US 160 to the south
  • A limited, local access route, Gunnison CR 26, is in place for travel. Up-to-date travel times are posted to bit.ly/us50bridge and the Gunnison County bridge closure page at https://www.gunnisoncounty.org/1078/Hwy-50-Bridge-Closure. No public travel will be allowed outside of the times posted.
    • Oversize/overweight vehicles will only be allowed on CR 26 with a permit on Wednesdays per Colorado Department of Transportation regulations. https://leg.colorado.gov/content/size-and-weight-limitations
    • No Placarded Hazardous Materials loads per Colorado Department of Transportation regulations
    • Prohibited vehicles will need to use detours on I-70 or US 160 to travel between Gunnison and Montrose.

Media kit available by emailing [emailprotected].

Resources for Information and Updates

For additional information about this project:

Know Before You Go

Travelers are urged to “know before you go.” Gather information about weather forecasts and anticipated travel impacts and current road conditions prior to hitting the road. CDOT resources include:

Download the COtrip App!

The new free COtrip Planner mobile app was designed to meet the growing trend of information on mobile and tablet devices for the traveling public. The COtrip Planner app provides statewide, real-time traffic information, and works on mobile devices that operate on the iOS and Android platforms. Visit the Google Play Store (Android devices) or the Apple Store (iOS devices) to download!

CDOT makes substantial progress ahead of US 50 Blue Mesa Middle Bridge limited opening (2024)

FAQs

Is the bridge over Blue Mesa Reservoir open? ›

The bridge is now open in a limited capacity. A pilot car will lead small vehicles across one lane for 12 hours a day, from 6:30 a.m. to 6:30 p.m. Starting July 8, however, the bridge will only be open from 6:30 a.m. to 8:30 a.m. and 4:30 p.m. to 6:30 p.m.

Did CDOT close a bridge near Gunnison on Highway 50 due to cracks in the bridge? ›

CDOT closed the bridge at the urging of the Federal Highway Administration and state bridge engineering experts due to the findings of an ongoing safety inspection, which identified anomalies in the bridge on Thursday, April 18.

Is the Blue Mesa bridge reopening to limited traffic in July? ›

After the long holiday weekend, beginning Monday, July 8, the bridge will be open, and pilot cars will lead single-direction traffic each day from 6:30 a.m. to 8:30 a.m. and again from 4:30 p.m. to 6:30 p.m.

Is the bridge between Gunnison and Montrose open? ›

The bridge between Gunnison and Montrose near Dillon Pinnacles (known as Middle Bridge) opens twice a day to alternating traffic. Pilot cars will lead single-direction traffic each day from 6:30 a.m. to 9:30 a.m. and again from 4:30 p.m. to 7:30 p.m. Other than these hours, the bridge is closed.

Are they draining Blue Mesa Reservoir? ›

Colorado's largest lake, Blue Mesa Reservoir, was unceremoniously drained by the Bureau of Reclamation last year, but its level has risen over 50 feet, now just 30 feet below full capacity.

Is Kebler Pass open in 2024? ›

The standard restrictions will be in place for driving over Kebler Pass. The current plan is to have Kebler open Friday May 31, 2024, at 4:00 pm. Flaggers will be posted on both sides of Kebler Pass, Gunnison County Road 12.

What is the longest suspension bridge in Colorado? ›

Royal Gorge Bridge

What is the bridge between the mountains in Colorado? ›

956 feet above the crashing Arkansas River, the Royal Gorge Bridge — one of the world's highest suspension bridges — connects visitors from one side of the millions-plus-years-old gorge to the other, where even more adventure awaits.

When was the Blue Mesa bridge built? ›

The bridge was built in 1963 and state inspectors found a defect at milepost 136.3, and during a second inspection crews “identified anomalies in the bridge.” T1 steel is used in two Colorado bridges, both spanning portions of Blue Mesa Reservoir. What Do You Think?

Why is Blue Mesa Reservoir closed? ›

Bridge over Blue Mesa Reservoir slated to reopen July 3, after being closed more than two months. Hart Van Denburg/CPR News The Highway 50 bridge linking Montrose and Gunnison remained closed June 2, 2024, during repairs after a crack in the bridge was found earlier in the year.

Is Mesa Top Loop Road open? ›

The Mesa Top Loop Road is open daily, 8:00 am to sunset.

Is Cape Coral Bridge closed July 4? ›

The Cape Coral Bridge will be closing on Thursday starting at 3 a.m., and it will remain closed for 24 hours. If you usually take this bridge on your daily route, you already know it will now be one less bridge to use since the Caloosahatchee Bridge is also closed for construction.

Is the new Potomac River bridge open? ›

Opened on October 12, 2022, this 1.7-mile, four-lane bridge is located on US 301 and spans the Potomac River from Newburg, Md., to Dahlgren, Va.

Is Trail Bridge Reservoir open? ›

At a Glance. Current Conditions: Eugene Water and Electric Board (EWEB) has closed Trail Bridge Campground, Lakes End Campground, Trail Bridge Reservoir Boat Launch, and Smith Reservoir through Spring 2025 for work on the Carmen-Smith hydroelectric facilities.

How full is Blue Mesa Reservoir? ›

Elevation & ContentWater Inflow Data
Blue Mesa is 26.98 feet below Full Pool (Elevation 7519.40 ) By content, Blue Mesa is 71.94% of Full Pool (829,500 af)Total inflows for water year 2024: 840,889 acre feet This is 97.38% of the average of 863,507 acre feet
2 more rows

Is swimming allowed in Blue Mesa Reservoir? ›

A dip in Blue Mesa can be refreshing, but the water remains cold even in the summer. The shoreline of the reservoir is mostly steep and rocky, but there are few places particularly good for swimming.

References

Top Articles
Latest Posts
Recommended Articles
Article information

Author: Aracelis Kilback

Last Updated:

Views: 5607

Rating: 4.3 / 5 (64 voted)

Reviews: 95% of readers found this page helpful

Author information

Name: Aracelis Kilback

Birthday: 1994-11-22

Address: Apt. 895 30151 Green Plain, Lake Mariela, RI 98141

Phone: +5992291857476

Job: Legal Officer

Hobby: LARPing, role-playing games, Slacklining, Reading, Inline skating, Brazilian jiu-jitsu, Dance

Introduction: My name is Aracelis Kilback, I am a nice, gentle, agreeable, joyous, attractive, combative, gifted person who loves writing and wants to share my knowledge and understanding with you.